In December 2013 company "Teplohimmontazh" finished foundation casting and assambly of rails for the kiln of Krasnogvardeisky brick plant
From 25th of December the specialists of our company had started the eraction of kiln walls and kiln metal structures.
The material of working zone is the brik of The Borovichi Refractories plant.
Teplohimmontazh performs the full range of construction works and refractory works on a new brick plant in Krasnogvardeisk district, Belgorod region.
The new brick plant with capacity of 60 mln pieces / year is planed to start up in 2015.