Construction of the 130 m stack on Lebedinsky GOK

  • 29.12.2014 Participation in Exhibition "Cement. Concrete. Dry mixes"
  • 07.10.2014 Construction of the 130 m stack on Lebedinsky GOK
  • Start up of anchor fabrication line
  • 07.10.2014 Construction of 130 meter high discharge stack on Lebedinsky GOK (Metalloinvest)
  • 29.08.2013 Building of stack on MGOK (part Metalloinvest)
  • 29.08.2013 Building of silos (slip Form method)
  • 01.10.2014 Start up of dry refractory mixes line
  • News archive
  • 01.02.2015 Participation in the exhibition "Domestic building materials 2015"
  • 12.02.2015 Participation in the conference "Refractories for industry"
  • 16-20 June, 2015 Participation in THERMPROCESS 2015. Germany, Dusseldorf
  • 2015. Yuzhno-Kyrgyzskij Cement CJSC (Kyrgyz Republic) - Cement plant thorough overhaul

In september 2014 within 28 days our copmany constructed 130 heigh stuck  including refractory isolation.

Method of slipform was used.

The main stack and refractory isolation were performed simultaneously based on patented method of our company. 